The following statement was read by Dr. Elin Claggett during Public Comments at the November 16 meeting of the Caswell County Board of Commissioners.
In 2016, DOT plan for Hwy 86 was a 4 lane-divided highway for $114 million. This was subsequently downsized to a 3-lane project scheduled to begin in 2020. By Dec. 2022, DOT Division Project Manager emailed " . . . plans for Highway 86 are to construct passing lanes and shoulder improvements at various locations & . . . estimated project cost for the NC 86 project is $14.7 million." Today, the same R-5822 project costs have escalated to $26.6 million without significant change in scope.
The traffic light at Park Springs Rd. & Hwy 86N intersection and turn lane at the adjacent Solid Waste site required persistence. In 2021, I requested a 10-year NC DOT meta-analysis of accidents within 1/4 mile. Next, I received a 2-year log of 911 calls on 86N. For over a year, I emailed documentation & photos of accidents as they occurred to Mr. Wright & Mr. Robinson, DOT Division Engineers. Next, the Caswell Co. Manager sent letters to Congressmen Phil Berger & Graig Meyer. Finally, after a hit & run and nearby fatal head-on collision, the dollars were found and the work was completed. The cost was $100K for the turn lane and $400K for the 4-way traffic signal. On March 3, 2023, the Project Manager stated "The $500,000 previously mentioned should have been the totaled amount for the signal and the turn lane design, construction & installation.”
Hwy 86N & Old 86 intersection is only 7 miles south. The same traffic volume between Yanceyville & Virginia State Line has increased as Hwy 86 is nothing more than an on-ramp between I-40 (Hillsborough) & Danville’s Casino.
DOT’s proposed design has vehicles, including semi-trucks & ambulances, approach the intersection from opposite directions, turn right, make an U-turn in front of oncoming traffic and head back toward the same intersection. In contrast, alignment of crossroads and a 4-way traffic light should enable safer left turns in all directions. Alternatively, NC DOT studies show that roundabouts yielded 50% reduction in crashes & 80% reduction in fatalities & injuries. The initial cost is greater but balanced by elimination of electric bills & signal maintenance.
Another death does not need to occur before a decision to install a traffic signal or roundabout is made.
-Dr. Elin Claggett, Providence, NC